Project: BuckRV-8   -  
            Listing of Entries
    (Please mouse-over any icon to get a description of that function).



Categories
  
Builder Name:Buck Wyndham   -  
Project:   Vans - RV-8   -   VIEW REPORTS
Total Hours:3964.35
Start/Last Date:Jan 08, 2002 - No Finish Date
Engine:AeroSport Power IO-375-M1S
Propeller:Whirlwind 330-3B/72H-73 3-blade CS
Panel:G3X, G5, GTN650, GTR20, GTX45R, GMA245, GMC507
 
Friendly URL: https://eaabuilderslog.org?s=BuckRV-8

Home or Last Project Picture

Apr 03, 2020     Side panel layout - (2.5 hours)       Category: Instrument Panel
1. Laid out all components on the lower switch panels, and checked the clearances and ergonomic issues for each. On the left panel will be the fuel selector, carbon monoxide detector, and front seat heat switch. On the right side will be the circuit breakers for the Main and Essential buses, the USB charger ports, the 12V main battery charging port, and the USB port power switch.

2. I also checked a few clearances on the side panels, and discovered that the magneto switches have to be moved apart just a bit, because of the NASA-style switch guards I'll be using.

3. Figured out where the switches will be on the right lower panel.


 


NOTE: This information is strictly used for the EAA Builders Log project within the EAA organization.     -     Policy     -     © Copyright 2024 Brevard Web Pro, Inc.